Work continues on Lakewood Blvd.
DOWNEY - Work continues on Lakewood Boulevard between 5th Street and Florence Avenue as workers install new piping to transport recycled water.The contractor, Sully-Miller Contracting Company, has already installed a 12-inch recycled water mainline stretching 3,215 linear feet. New fire hydrants are also being installed and existing water meter services will be replaced. When all utility work is complete, new landscaped median islands will be constructed, new street and pedestrian safety lights will be installed and pavement rehabilitation work will begin. Construction is scheduled to be "substantially completed" by June.
********** Published: February 17, 2011 - Volume 9 - Issue 44